Highway 290 Truck Stop in Hockley, Texas
Project Timeline

Building sign installation completed.
Both fuel canopies are now fully framed and roofed, transforming the site and bringing the project one step closer to completion.
Two 40,000-gallon fuel tanks successfully installed in one day.

Canopy steel framing completed at the site.

Interior work is actively in progress at the site as flooring and paint work have completed.

Installation of steel pillars for the canopy is underway.

Exterior tile work is complete and interior work is actively underway.

Exterior tile work is underway.
Exterior panels and glass work are underway while interior paint work is underway.
Front sheathing finished, with siding and interior structure progressing on site.

Structural framing is actively progressing.

Decking work is underway.

350 yards poured overnight to stay on schedule. Deadline met.

Water pond construction completed. One more milestone checked.

From dusk to dawn, our crew kept the momentum going. Deadline met.

Crews are pouring concrete overnight to keep the foundation schedule moving.

Excavation and trenching are nearly finished, with utility lines being installed ahead of the concrete pour.

Clearing and early earthwork are in progress as the crew begins shaping the site for foundation and utility installation.