Kroozin C-Store in Katy, Texas
Project Timeline

Signage work on the main store building has completed.

Installation of 6 fuel dispensers is now complete at the site, marking another key milestone as the project moves closer to completion.
The project continues to progress with exterior tile work completed, panel installation nearing completion, 150 yards of driveway concrete poured, and interior paint work underway.
Exterior tiling and panel work is underway.
Metal framing and canopy concrete prep underway.
Metal framing and canopy construction are underway at the site.

Fuel tank deployment executed with accuracy and control.
Concrete pour continues as CMU wall installation begins

Every build starts with a solid foundation. Katy C-Store concrete pour in motion.

At the new Katy C-Store project, we’re pushing forward — rain or shine.