Kroozin C-Store in Katy, Texas
In Progress

Kroozin C-Store in Katy, Texas

Progress Updates

Project Timeline

2026-05-25T00:00:00.000Z
2026-05-25T00:00:00.000Z

Signage work on the main store building has completed.

2026-05-04T00:00:00.000Z
2026-05-04T00:00:00.000Z

Installation of 6 fuel dispensers is now complete at the site, marking another key milestone as the project moves closer to completion.

2026-04-27T00:00:00.000Z
2026-04-27T00:00:00.000Z

The project continues to progress with exterior tile work completed, panel installation nearing completion, 150 yards of driveway concrete poured, and interior paint work underway.

2026-04-10T00:00:00.000Z
2026-04-10T00:00:00.000Z

Exterior tiling and panel work is underway.

2026-03-30T00:00:00.000Z
2026-03-30T00:00:00.000Z

Metal framing and canopy concrete prep underway.

2026-03-10T00:00:00.000Z
2026-03-10T00:00:00.000Z

Metal framing and canopy construction are underway at the site.

2026-02-20T00:00:00.000Z
2026-02-20T00:00:00.000Z

Fuel tank deployment executed with accuracy and control.

2026-01-15T00:00:00.000Z
2026-01-15T00:00:00.000Z

Concrete pour continues as CMU wall installation begins

2025-12-19T00:00:00.000Z
2025-12-19T00:00:00.000Z

Every build starts with a solid foundation. Katy C-Store concrete pour in motion.

2025-11-29T00:00:00.000Z
2025-11-29T00:00:00.000Z

At the new Katy C-Store project, we’re pushing forward — rain or shine.